IDHeadlineDateTrailsSegmentsLinksActions
1CPX Announced

May 2014

11
2CPX Opened

July 10, 2023

11
3Conceptual Designs

October 2022

21
4Construction Funded

January 2024

    01
    5Framingham purchases CSX railway

    December 2022

    11
    625% Design Started

    May 2024

    11
    7Expected Opening

    May 2025

    10
    8Duplicate event, delete

    May 2022

      01
      9Construction Started

      April 2024

      11
      1075% Design Begins

      March 2024

      10
      11Phase 1 Construction Begins

      November 2022

      11
      1225% Design

      July 22, 2022

      12
      13Completed

      2010

      10
      14Construction Begins

      2026

      10
      15Completed

      2010

      10
      16Fitchburg Cutoff Path Opened

      August 2013

      11
      17Phase 2 Construction Begins

      February 24, 2025

      11
      1825% Design Meeting

      February 3, 2024

      11
      19100% Design

      February 2025

      10
      20Construction Expected to Begin

      2027

        01
        21Purchased by East Quabbin Land Trust

        2007

        12
        22Clinton Tunnel Purchased

        June 3, 2024

        11
        23Construction Authorization

        December 4, 2024

        11
        24Feasibility Study Grant

        June 2023

          10
          25Feasability Study Completion

          June 2025

            10
            26Expected completion

            April 2025

            10
            27Conceptual Designs Released

            November 14, 2022

              11
              29Expected start of construction for Phase 3

              2029

              11
              30Ribbon Cutting

              November 19, 2021

                11
                31Construction plans released

                November 2024

                15
                32Introductory Public Presentation

                June 7, 2022

                12
                33Conceptual Design Public Meeting

                November 16, 2022

                11
                34Advanced Design Public Meeting

                June 8, 2023

                12
                35Path opens

                1985

                10
                36Opened

                2024

                  10
                  38MassTrails Grant for MCRT Design

                  June 14, 2023

                  11
                  39Hudson Bicycle & Pedestrian Committee Report

                  January 23, 2023

                  21
                  40Public Information Meeting #2

                  November 4, 2021

                  12
                  4125% Design Public Hearing

                  March 7, 2024

                  12
                  42Phase 3 Construction Complete

                  2022

                  10
                  4325% Design Presentation

                  July 21, 2022

                  12
                  44MCRT Gibbs Crossing in Ware opens

                  September 8, 2023

                  11
                  45MCRT Gilbertville Fitness Trail opens

                  October 25, 2014

                  11
                  46Completed

                  2014

                  11
                  47Completed

                  2023

                  21
                  48Stone dust trail completed by Town of Wayland

                  April 2017

                  11
                  49Funding for Design + Permitting

                  January 10, 2025

                  51
                  50Phase 1 Complete

                  2020

                  10
                  51Construction to begin on Sudbury-Weston paved connection

                  August 2027

                  21
                  52MCRT Ware River Park segment opens

                  September 26, 2023

                  11
                  53Phase 1 Construction Completed

                  November 1, 2024

                  10
                  54Design Grant

                  June 2022

                  10
                  55Funded for Preliminary Design

                  June 2024

                  11
                  56Expected to be Paved

                  June 30, 2025

                  11
                  5725% Design of Sudbury-Wayland Submitted

                  May 2022

                  21
                  58Completed

                  October 19, 2019

                  11
                  59Phase 1 Funding

                  2020

                  10
                  60MCRT Expansion Opened

                  September 8, 2022

                  11
                  61Phase 2 Complete

                  2022

                  10
                  62Clinton Purchases Right-of-way

                  December 18, 2020

                  11
                  63Public Forum

                  May 18, 2023

                  12
                  64Information Sessions

                  April 15, 2017

                  20
                  65State Admits Designs Still in Progress

                  April 2024

                  12
                  66Town Meeting Approves Design Funding

                  May 15, 2017

                  20
                  67State Officials Confirm 2024 Construction

                  June 2023

                  11
                  68Design Expected from MassDOT

                  2025

                  11
                  69Applied for Federal RAISE Grant

                  July 2021

                  11
                  70Town-Wide Vote Upholds Funding

                  June 29, 2017

                  20
                  71MassDOT Shares Early Designs

                  November 22, 2021

                  11
                  72RAISE Grant Declined

                  November 2021

                  10
                  73Construction Began

                  July 2024

                  11
                  74Pre-75% Design Meeting + Site Walk

                  June 11, 2024

                  12
                  75Feasability Study

                  January 1, 2002

                  20
                  76Governor Commits to Funding

                  October 22, 2021

                  11
                  77Construction Funding Approved for FY 2026

                  May 26, 2022

                  10
                  78Expected Completion

                  Fall 2025

                  11
                  79Belchertown backs completion of Mass Central Rail Trail

                  February 2022

                  11
                  80Franklin Town Council approves funds to purchase SNETT extension

                  December 12, 2024

                  11
                  81Grant for Design Awarded

                  2022

                  11
                  82Negotiations Ongoing

                  2016

                  21
                  83Project out for Bid

                  January 2025

                  11
                  84Construction Planned

                  2023

                    01
                    85Start of Construction

                    Spring 2023

                    11
                    86Trail Nearly Complete

                    Spring 2024

                    11
                    87Completion Expected

                    Fall 2025

                    11
                    88Construction Expected

                    May 2025

                    10
                    89Right-of-way Aquired

                    August 1, 2019

                    21
                    90Rail Trail Efforts Begin

                    2007

                    20
                    91Ribbon Cutting Ceremony

                    September 4, 2024

                    11
                    92Weston Select Board signs letter in support of Mass Central Rail Trail

                    2025

                    11
                    93Sudbury Town Meeting votes three times in favor of the Mass Central Rail Trail

                    2014

                    13
                    94West Lake Washacum Bridge Replaced

                    2022

                    11
                    95Pommogussett Tunnel Installed

                    August 11, 2011

                    11
                    96Eversource files permits to build gravel road

                    2016

                    11
                    97Stone dust or paved in Sudbury?

                    May 11, 2015

                    11
                    98Massachusetts Passes Climate Law for Clean Energy Transition

                    November 21, 2024

                    22
                    99Weston votes against the Wayside Rail Trail

                    December 8, 1997

                    123
                    100DCR endorses the buried power reliability proposal

                    April 2017

                    12
                    101EFSB approves Sudbury-Hudson buried power reliability project

                    December 18, 2019

                    10
                    102Central Massachusetts Rail Trail Feasibility Study, and formation of Wayside Rail Trail Committee

                    April 1997

                    121
                    103Culvert after Miles Road built

                    May 23, 2024

                    11
                    104Weston works on Conant Road feasibility study

                    2017

                    11
                    105DCR leases the Mass Central Rail Trail - Wayside

                    December 30, 2010

                    121
                    106Charnock Tunnel Installed

                    August 21, 2006

                    11
                    107Bruce Freeman advocates for the "Lowell-Sudbury Rail Trail"

                    June 1985

                    41
                    108Golden Spike 2002

                    2002

                    11
                    109Eversource buried power reliability project proposed

                    2015

                    11
                    110Ware River Bridge Installed

                    March 2013

                    11
                    111Construction survives lawsuits 2017-2023

                    July 2023

                    11
                    112Alewife Brook Greenway opens

                    October 2012

                    11
                    113BFRT Phase 2A Opens

                    April 3, 2018

                    10
                    114BFRT Phase 2C Opens

                    September 27, 2019

                    10
                    115BFRT Phase 2B Opens

                    May 2023

                    10
                    116BFRT Phase 1 Opens

                    August 29, 2009

                    10
                    117Sudbury votes to purchase CSX land

                    April 8, 2008

                    11
                    118Sudbury votes for design and construction of Phase 3

                    March 26, 2024

                    11
                    119Sudbury votes for partial 75% design of Phase 2D

                    May 4, 2016

                    11
                    1204 Positive Sudbury Town Meeting Votes

                    March 22, 2022

                    24
                    121Sudbury votes for two resolutions for Phase 2D

                    May 8, 2012

                    12
                    122Sudbury votes for design of Phase 2D

                    March 7, 2017

                    11
                    123Sudbury Ballot Overwhelming Yes

                    March 26, 2012

                    11
                    124Sudbury votes to Expedite Completion of Phase 2D

                    September 12, 2020

                    11
                    125Sudbury votes for preliminary design of Phase 3

                    March 16, 2023

                    11
                    126Sudbury votes for design of Phase 2D, again

                    October 15, 2018

                    11
                    127Sudbury votes to use Community Preservation Funds for design

                    May 7, 2014

                    11
                    128Trail built, becomes Shining Sea Bikeway

                    1975

                    11
                    129Massachusetts passes rail trail protection laws in response to controversy

                    September 1973

                    13
                    130Shining Sea Bikeway built to North Falmouth

                    2009

                    11
                    131Falmouth wins at Massachusetts Supreme Judicial Court

                    June 21, 1973

                    12
                    132Falmouth votes to take the railroad by Eminent Domain

                    April 2, 1969

                    11
                    133First proposal to abandon NH Railroad, Falmouth trail first proposed

                    1965

                    11
                    134Private sale of Falmouth ROW announced

                    April 3, 1969

                    11
                    135Additional builds of the Shining Sea Bikeway

                    1998

                    11
                    136CSX Derailment South of Route 20 in Sudbury

                    2000

                    21
                    137Sudbury begins Bruce Freeman Rail Trail planning

                    2004

                    11
                    138MBTA Central Mass Commuter Rail Feasibility Study

                    December 1996

                    121
                    139Sudbury votes for Question 3: CSX Purchase

                    November 3, 2020

                    11
                    140Bruce Freeman Bike Path becomes Massachusetts law

                    April 1989

                    41
                    141"Sudbury Citizens for Responsible Land Stewardship" forms

                    2004

                    20
                    142Stow endorses power reliability project and MCRT

                    June 7, 2017

                    11
                    143Hudson endorses completion of the Mass Central Rail Trail

                    January 2025

                    31
                    144Waltham funds construction of 2.75 miles of the MCRT-Wayside

                    2022

                    31
                    145ARRT in Hudson built

                    September 24, 2005

                    21
                    146Start of the Assabet River Rail Trail

                    1992

                    41
                    147Recreational easement for ARRT Track Road established

                    July 27, 2009

                    11
                    148First ARRT section in Marlborough completed

                    May 17, 2001

                    11
                    149Acton and Maynard section opens

                    August 10, 2018

                    11
                    150Pave Track Road in design phase

                    2021

                    12
                    151ARRT Feasibility Study and positive vote in all Five towns

                    1997

                    41
                    152Congress Approves Redirecting Highway Funding to Transit

                    1973

                    10
                    153Path First Proposed

                    2011

                    12
                    154Construction Expected to Begin

                    2025

                    10
                    155MassTrails Grant

                    June 2023

                    11
                    156Trail Extended into NH

                    2005

                    10
                    157Passenger Rail Service Discontinued

                    1977

                    10
                    158Construction Begins

                    2013

                    10
                    159Southwest Corridor Park Action Plan

                    June 2024

                    12
                    160Trail is Paved

                    2002

                    10
                    161Right-of-Way Purchased

                    1987

                    10
                    162Opening Ceremony

                    September 15, 2016

                    11
                    163Construction Delayed

                    2014

                    11
                    164End of Freight Service

                    1982

                    10
                    1651950s-1960s: Highway Planned & Protested

                    1960

                    10
                    166Newton Takes Over Construction

                    Fall 2015

                    11
                    167New Orange Line Route Opens & Some Park Segments Complete

                    1987

                    10
                    168Arlington–Lexington Section Opens

                    September 1992

                    10
                    169Ribbon Cutting

                    May 5, 1990

                    10
                    170Alewife Extension Opened

                    1998

                    10
                    171Construction Begins

                    1979

                    10
                    172Lexington–Bedford Section Opens

                    May 1993

                    10
                    173Official Opening

                    October 25, 2002

                    10
                    174Highway Project Cancelled

                    1969

                    10
                    175Freight Rail Service Discontinued

                    1981

                    10
                    176Construction Begins

                    1991

                    10
                    177100% Design Submitted

                    January 5, 2024

                    10